Printer C % = 100 − 25 − 30 − 35 = 10% 10% → 12 × 10 = 120
80 posters → 1 h 120 posters → 1 ÷ 80 × 120 = 1.5 h
The table shows the printing rate of 4 printers. The rate for Printer D is not shown. The pie chart shows the total number of posters printed by each of the printers on a particular day. All the printers printed for 6 hours, except for Printer C which broke down after some time. (b) How many hours did Printer C print before breaking down? (2 marks)
Printer C % = 100 − 25 − 30 − 35 = 10% 10% → 12 × 10 = 120
80 posters → 1 h 120 posters → 1 ÷ 80 × 120 = 1.5 h