The graph below shows the number of cakes baked by Oven A and Oven B. There was an order for 540 cakes to be baked. In the first 30 minutes, cakes were baked in both Oven A and Oven B. Then, Oven A broke down. In the next 2 hours, only Oven B continued to bake cakes at the same rate. At what time would Oven B complete the order of baking the 540 cakes? (2 marks)
Answer: 00 30
Workings
Loading drawing…
Loading drawing…
3 gaps → 12
1 gap → 12 ÷ 3 = 4
oven B in 30 mins (0830 to 0900) → 44 - 28 = 16 cakes
1030 → 92
remaining → 540 - 92 = 448
16 cakes Oven B → 30 mins
448 cakes Oven B
→ 448 ÷ 16 x 30
= 840 mins = 14 hours
1030 + 14 hours = 0030